Tunnel monitoring „Galleria Dragonato“

Permanent surveillance ensures the safety of railway traffic

Back

The current clearance gauge of the Swiss Federal Railway’s Dragonato tunnel is not up to next-generation standards according to the ongoing “4 m corridor” program. In addition, the tunnel’s structural integrity has deteriorated to the point where the long-term safety of the railway traffic is of increased concern. Consequently, an upgrade project is underway to build a new tunnel which encloses the existing tunnel walls. After completion of this work, the old tunnel structure will be dismantled.

During the work on the new tunnel, the existing tunnel structure and the temporary catenary pylons are being monitored by an automated measurement system. The relevant survey points are placed along the tunnel wall in regular cross-section profiles. Furthermore, track alignment and other critical objects on the construction site are checked by periodic manual surveys.

Our services

  • Planning, installation and operation of the automated measurement systems
  • Automated monitoring of the tunnel structure and catenary masts
  • Manual deformation measurements of railway tracks and other infrastructure elements
  • Automated alerting system at threshold exceedance: text message, siren, warning light

SwiMo - Berlin Hauptbahnhof

Monitoring the construction of S21 at Berlin main station

Berlin, Germany
Deutsche Bahn AG
2015 - 2026
Learn more
SwiMo - Zermatt Bergbahnen

Monitoring mountain railways Zermatt

Zermatt, Switzerland
Zermatt Bergbahnen AG
2018 - ...
Learn more
SwiMo - Bhf Wthur Personenunterführung

Winterthur main station, Monitoring construction of pedestrian underpass

Winterthur, Switzerland
STRABAG AG, Schlieren
2018 - 2022
Learn more
SwiMo - Inselspital BB12

Monitoring new building Inselspital BB12, Bern

Bern, Switzerland
Inselspital, Infrastructure Directorate
2017 - 2020
Learn more
SwiMo - Hotel Palace Luzern

Monitoring Rebuilding Hotel Palace, Luzern

Luzern, Switzerland
Civil Engineer: Itten + Brechbühl, Zürich
2018 - 2020
Learn more
SwiMo - Gubrist 3. Röhre

Monitoring at new Gubrist tunnel

Zürich, Switzerland
Federal Roads Office (FEDRO)
2016 - 2022
Learn more
SwiMo - Bern Wylerfeld

Reconstruction of rail track intersection Wylerfeld, Berne

Berne, Switzerland
Swiss Federal Railway
2015 - 2021
Learn more
SwiMo - NAGRA GPS-Monitoring

NaGNet GPS-Monitoring

North of Switzerland & South-Germany
NAGRA, Switzerland
2010 - 2024
Learn more
SwiMo - Bern Murtenstrasse

Railway track and excavation pit monitoring Murtenstrasse Bern

Bern, Switzerland
Gross Generalunternehmung AG
2016 - 2019
Learn more
SwiMo - GNSS Moosfluh

GNSS Monitoring Ropeway Moosfluh

Riederalp, Switzerland
Aletsch Bahnen/PLANAX AG
2015 - ...
Learn more
SwiMo - AlpTransit Staumauermonitoring

AlpTransit Gotthard Dam Safety Monitoring

Gotthard region, Switzerland
AlpTransit Gotthard AG & Axpo AG
2000 - ...
Learn more
SwiMo - Chur Kantonsspital

Hospital „Kantonsspital Graubünden“, SUN extension project

Chur, Switzerland
Kantonsspital Graubünden
2014 - 2017
Learn more
SwiMo - Dortmund Hauptbahnhof

Railway track monitoring Dortmund main station

Dortmund, Germany
Civil engineering department of Dortmund
2014 - 2017
Learn more
SwiMo - Bellinzona Dragonato

Tunnel monitoring „Galleria Dragonato“

Bellinzona, Switzerland
Swiss Federal Railways
2017 - 2019
Learn more
SwiMo - Stalvedro

Rock face monitoring

Stalvedro, Switzerland
Federal Roads Office FEDRO
2015 - 2018
Learn more

Learn more

All references
SwiMo - Berlin Hauptbahnhof

Monitoring the construction of S21 at Berlin main station

Berlin, Germany
Deutsche Bahn AG
2015 - 2026
Learn more
SwiMo - Zermatt Bergbahnen

Monitoring mountain railways Zermatt

Zermatt, Switzerland
Zermatt Bergbahnen AG
2018 - ...
Learn more
SwiMo - Bhf Wthur Personenunterführung

Winterthur main station, Monitoring construction of pedestrian underpass

Winterthur, Switzerland
STRABAG AG, Schlieren
2018 - 2022
Learn more
SwiMo - Inselspital BB12

Monitoring new building Inselspital BB12, Bern

Bern, Switzerland
Inselspital, Infrastructure Directorate
2017 - 2020
Learn more
SwiMo - Hotel Palace Luzern

Monitoring Rebuilding Hotel Palace, Luzern

Luzern, Switzerland
Civil Engineer: Itten + Brechbühl, Zürich
2018 - 2020
Learn more
SwiMo - Gubrist 3. Röhre

Monitoring at new Gubrist tunnel

Zürich, Switzerland
Federal Roads Office (FEDRO)
2016 - 2022
Learn more